Skip to content
Tenfell
Awarded contract
Published 24 Oct 2023

Subsea vs Floating Substations - Technoeconomic Comparison - ORE/23/013

Offshore Renewable Energy Catapult · United Kingdom

Key facts

Contract value
£94,744
Awarded
07 Feb 2024
Contract starts
08 Feb 2024
Contract ends
22 Feb 2025
Procedure
Open procedure
Buyer type
Utilities & transport

Awarded to

SupplierValue
Crondall Energy Consultants£94,744

Description

The Consultant will be required to define the floating and subsea systems for two case study sites. For consistency, baseline sites from previous FOW CoE projects will be used where possible. Gaps in knowledge and technology will be identified to define a roadmap towards commercial readiness by 2025 to 2030. Experience from previous/ongoing projects will play a key role in this task e.g. previous OREC projects on inter-array cable topology (DC06) and mooring and cable installation (DC07). Key uncertainties in this roadmap should also be defined. A cost comparison should be performed to set out which option would be preferable for a range of potential UK project configurations, subject to a range of assumptions and sensitivities. Finally, a sensitivity of lifetime costs to system reliability levels will be investigated.

Categories (CPV)

Similar open tenders

About Offshore Renewable Energy Catapult

Their tenders, awards, contracts coming up for renewal, decision makers and committee papers.

View buyer profile

Published by the buyer on Contracts Finder (Open Government Licence v3.0). Always read the original notice before responding.