Description
The following gives an outline description of the works: Stage 1 - Carry out a conditional survey of each mast including all fixings, connections, guys ropes and anchorage point and then report on the suitability of the masts in their current condition. Stage 2 - Disconnect top antenna wires running between all three masts. This work must be undertaken by a competent nominated antenna contractor. The removal of the antenna wires shall allow NLB Staff to undertake tuning tests to establish whether the station can be run using only the central mast.
The outcome of the works at this stage shall determine the scope and timescales for further works, there are three possible options as listed: Option 1 Should the trials prove unsuccessful the antenna wires shall be re-connected and then stage 3a of the works shall be implemented. Option 2 Should the trials show a strong indication that using only the central mast will be successful the refurbishment/demolition works shall be delayed for 4 weeks to allow NLB personnel to monitor the results. After this period Stage 3b of the works will be implemented as advised by NLB Rep. Option 3 Should the trials prove inconclusive the NLB retain the option to extend the trial period to 6 months after which time the works will move on to either stage 3a or 3b as determined by NLB Rep. All tenderers should take note of the above and price in accordance particularly in relation to mobilisation of site. Stage 3a - Refurbishment of all three masts as detailed in the Bill of Quantities. Stage 3b - Refurbishment of the central mast only with the outer masts being taken down and removed from site as outline in the Bill of Quantities. Stage 4 - Demobilisation and site clearance
Site visits will be conducted on Wednesday 3 August 2016 for this project. Please contact Ruth Millan, [email protected] to confirm attendance.
Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs). However, any selection of tenderers will be based solely on the criteria set out for the procurement. The tender documents can be downloaded from our buyer profile http://nlb.g2b.info, current tenders, other information
Categories (CPV)
Similar open tenders
Donegal County Council - Supply and Delivery of Workshop Tools and Miscellaneous Items
Location: IrelandBuyer: Donegal County Council
Open tenderCloses 2 Dec, 202627 daysValue €60.00KSource TEDSupply and Delivery of Workshop Tools and Miscellaneous Items such as socket sets, wheel alignment gauges, impact wrenches, angle grinders, welding equipment, inspection lamps, wheel removal trolleys, starter packs, trolley jacks and heat torches etc.
Supply of Cabins to a holiday rental business in County Carlow
Location: IrelandBuyer: Bilboa Hills Ltd
Open tenderCloses 3 Dec, 202628 daysValue €250.00KSource TEDSupply of 4 Cabins to a glamping enterprise in County Carlow
Tender 23/2026 - SUPPLY AND DELIVERY OF WORKSHOP TOOLBOXES COMPLETE WITH TOOLS
Location: Northern IrelandBuyer: Newry, Mourne and Down District Council (NMD)
Open tenderCloses 2 Dec, 202627 daysSource Find a TenderNewry, Mourne and Down District Council invite suppliers to tender for the provision of a total of 10 toolboxes complete with tools. This is to equip the workshop personnel with the appropriate tooling to maintain Council vehicles, plant, and equipment to a high standard in line with industry guidelines and statutory r
BBV Sublot 4 - HSST1020 - SALTLEY VIADUCT GABION WALL
Buyer: Balfour Beatty VINCI JV HS2
Open tenderCloses 13 Nov, 20268 daysValue £1.00mSource Contracts FinderOpportunity Summary - Gabion Retaining Wall Works We are seeking experienced suppliers and subcontractors to provide the supply, delivery and installation of a gabion retaining wall system as part of a civil engineering project. Scope of Requirements The successful supplier shall be responsible for: Supply
Supply of EURO Heavyweight and Lightweight Pallets for West Midlands Fire and Rescue Authority 2026 - 2030
Location: United KingdomBuyer: West Midlands Fire and Rescue Authority
Open tenderCloses 4 Dec, 202629 daysValue £250.00kSource Find a TenderWest Midlands Fire and Rescue Authority (the Authority) is seeking to award a Contract for the provision of Euro Heavyweight and Lightweight pallets.
Provision of Surface Dressing Chips
Location: ScotlandBuyer: Tayside Contracts
Open tenderCloses 2 Dec, 202627 daysValue £500.00kSource Public Contracts ScotlandTayside Contracts requires suitably experienced Suppliers to provide a reliable, responsive and cost-effective supply of Surface Dressing Chips for use on annual road maintenance and surface dressing programmes undertaken on behalf of Angus Council, Dundee City Council, Perth & Kinross Council and other external client