The review of Westinghouseâs validation evidence for the effectiveness of the AP1000 passive reactor heat removal system
Department for Work and Pensions · London
Key facts
- Contract value
- £73,744
- Awarded
- 25 Jun 2015
- Contract starts
- 30 Jun 2015
- Contract ends
- 30 Nov 2015
- Procedure
- Not applicable
- Buyer type
- Central government
Awarded to
| Supplier | Value |
|---|---|
| Amec Foster Wheeler | £73,744 |
Description
1.1 In 2007, Westinghouse (WEC) submitted its AP1000 reactor design to ONR for a phased Generic Design Assessment (GDA). This culminated in 2011 with ONR publishing a suite of Step 4 technical assessment reports, an interim Design Acceptance Confirmation (iDAC) and the 51 outstanding GDA Issues which must be resolved before ONR will consider granting a âfullâ DAC. On reaching this point, WEC paused its GDA related activities. In 2014, WEC requested to resume GDA to support the Moorside project. 1.2 In the event of a plant transient, the AP1000 is designed such that core decay heat removal is normally accomplished by the (active) startup feedwater system. However, if that system is not available (for example, due to a loss of all ac electrical power), emergency core decay heat removal is provided by the Passive Residual Heat Removal (PRHR) heat exchanger. The PRHR heat exchanger is a C-tube heat exchanger connected, through inlet and outlet headers, to the reactor coolant system. The inlet to the heat exchanger is from the reactor coolant system hot leg, and the return is to the steam generator outlet plenum. The heat exchanger is located above the core to provide natural circulation flow when the reactor coolant pumps are not operating. The In Containment Reactor Water Storage Tank (IRWST) provides the heat sink for the heat exchanger. After the IRWST water reaches saturation (in about two and half hours), steam starts to vent to the containment atmosphere. The condensation that collects on the containment steel shell (cooled by the passive containment cooling system) returns to the IRWST, maintaining fluid level for the PRHR heat exchanger heat sink. The extant safety documentation submitted to ONR during the initial GDA period (Ref 1, Section 15.2.6) made a claim that by these means, the PRHR heat exchanger, in conjunction with the passive containment cooling system, would be able to keep the reactor coolant subcooled indefinitely.
1.3 ONR fault studies inspectors investigated this claim during GDA Step 4 (Ref 2, notably section 4.2.3.3). They found that Ref 1 did not include a design basis assessment of the passive containment cooling system for such plant transients or a substantiation of the efficiency with which re-condensed water is collected and recycled back to the IRWST. As a result, amongst the 51 GDA Issues is GI-AP1000-FS-06 (Ref 3) which requires WEC to provide validation evidence showing that the IRWST is functionally capable of cooling the PRHR during intact circuit faults for 72 hours.
Categories (CPV)
- 73000000 Research and development services and related consultancy services
Similar open tenders
Pay and Reward Strategy
Location: LondonBuyer: Office of Rail and Road
Open tenderCloses 3 Dec, 202628 daysValue £55.00kSource Find a TenderThe Office of Rail and Road has committed to carry out a comprehensive review of its Pay and Reward Strategy for all pay grades below the Senior Civil Service (SCS). The aim is to ensure that ORR has a strategy in place that delivers an equitable and consistent approach to pay and reward which is understood and suppor
Research Services for Pensions illustrations: presenting uncertainty and variability
Location: LondonBuyer: THE FINANCIAL REPORTING COUNCIL LIMITED
Open tenderCloses 7 Dec, 202632 daysValue £125.00kSource Find a TenderThe Financial Reporting Council (FRC) regulates auditors, accountants and actuaries and sets the UK's Corporate Governance and Stewardship Codes. As the Competent Authority for audit in the UK, we set auditing and ethical standards and monitor and enforce audit quality. The FRC requires Research Services to examine how
AI Creator Control
Location: WalesBuyer: Intellectual Property Office
Open tenderCloses 28 Nov, 202623 daysValue £80.00kSource Find a TenderThe IPO requires a supplier to provide research to support this review. The intention is that this will be a four-month project including an interim report (shared with policy officials) and final report (prepared for external publication). The Government may wish to communicate initial findings from the interim report
Mapping the Research and Innovation Ecosystem in select North African countries Priorities Actors and Uk Partnership Opportunities in Algeria Egypt Morocco and Tunisia
Location: LondonBuyer: British Council
Open tenderCloses 25 Nov, 202620 daysValue £70.00kSource Find a TenderThe British Council invites proposals to conduct a market intelligence study titled Mapping the Research and Innovation Ecosystem in Selected North African Countries Priorities Actors and Uk Partnership Opportunities covering Algeria Egypt Morocco and Tunisia
Westgate Vision 2040 - Multi-Disciplinary Design Team (MDDT) Consultancy Service
Location: IrelandBuyer: Louth County Council
Open tenderCloses 25 Nov, 202620 daysValue €900.00KSource TEDDelivery of detailed design, tender and management of construction phase to handover for Westgate Vision Public Realm Scheme Character Area 1 and 2
Ireland West SDZ Designated Activity Company DAC is seeking consultancy services to support the development of an Aviation Circular Economy Hub at Ireland West Airport Knock.
Location: IrelandBuyer: Mayo County Council
Open tenderCloses 24 Nov, 202619 daysValue €125.00KSource TEDMCC are publishing this competition on behalf of Ireland West SDZ Designated Activity Company. The brief is to undertake the market validation, technical, commercial and operational planning development work necessary to establish the proposed Hub’s viability. The tenderer shall identify an appropriate operating model