EV076 Killingworth Sustainable Retrofit Project Sub-Contractor Packages- Block A 02. Mechanical

North Tyneside Council · North East

Key facts

Contract value
£994,282
Awarded
12 Feb 2020
Contract starts
13 Feb 2020
Contract ends
31 Aug 2020
Procedure
Open procedure
Buyer type
Local government

Awarded to

SupplierValue
H Malone & Sons Ltd£994,282

Description

The Authority has secured funding from the European Regional Development Fund (ERDF) for the Killingworth Site Sustainable Retrofit project. This project is a combination of refurbishment and replacement of the existing office accommodation, workshop, welfare and other facilities on the site ensuring it 'future proofs' its operations, with energy efficiency and functionality as the key principles using a range of energy efficient systems, alongside energy generation and energy storage/distribution solutions to support a move to an electronic powered operational fleet.

This procurement opportunity relates specifically to the New Mechanical, Plumbing and Heating Installation, including ventilation, Air Conditioning, Sanitary ware and above ground drainage. North Tyneside Council will be the Principal Contractor for the project therefore tenderers should note that they will be working in the capacity of Sub-Contractor.

Tenderers must be aware that this is an operational site and as such Works must be undertaken taking into consideration neighbouring occupied buildings, vehicle movements and office and field-based employees accessing and attending the site in vehicles and on foot. The Block A site is very restrictive for access / plant movements and therefore it is strongly recommended that Tenderers undertake a site visit, contact details to make arrangements are contained within the Preambles document in the tender pack.

Tenderers will be required to confirm that they will comply will the Authority's minimum standards in relation to health & safety and mandatory training requirements. All operatives must hold CSCS cards, asbestos awareness training certification and any other trade/task specific relevant qualifications.

The full programme of Works are to be completed between 06/01/2020 and 31/08/2020.

Additional information: The Documentation is available to access and download immediately once organisations have registered their interest in this opportunity via the ProContract electronic Tendering Portal ONLY and the, website https://procontract.due-north.com

https://procontract.due-north.com/Advert?advertId=a8fc375b-dd0a-ea11-80fb-005056b64545

Categories (CPV)

Similar open tenders

About North Tyneside Council

Their tenders, awards, contracts coming up for renewal, decision makers and committee papers.

View buyer profile

Published by the buyer on Contracts Finder archive (Open Contracting) (Open Government Licence v3.0). Always read the original notice before responding.