A47 Guyhirn Junction Groundworks Package

galliford try

Key facts

Closing date
20 Oct 2020
Contract starts
01 Feb 2021
Contract ends
01 Sep 2021
Procedure
Open procedure (below threshold)
Buyer type
Other public body

Description

A47 GUYHIRN JUNCTION SCHEME NOTIFICATION OF SUBCONTRACT GROUNDWORKS PACKAGE

The A47 Guyhirn Junction Project is the first of series of 5 projects on the A47 Corridor that Galliford Try are delivering with Highways England through the Regional Delivery Programme - East. The project involves increasing the size of the existing roundabout and approaches to improve capacity. The roundabout is situated at the junction with the A141 some 20km east of Peterborough To enable to successful delivery of the project we are seeking to procure a specialist groundworks subcontractor with experience of delivering major highways projects. The scope of works will involve:- We are seeking to procure a Groundworks Package for the works that will encompass the following elements:

• Main Compound Establishment • Enabling Works • General site clearance • Drainage • Earthworks • Sub Base • Kerbs & Footways (excl bituminous surfacing) • Ducts & Chambers for Street Lighting & Traffic Signal installation • Attendance on Statutory Undertakers (details tbc)

The project is forecast to commence on site in February 2021 Subcontractors bidding for this opportunity will be required to demonstrate their capability and capacity for successfully delivering a project of this size and nature and provide examples of similar projects. Timings Deadline for Notifications of Interest 17:30hrs Tuesday 20th October 2020 Deadline for tender submission 17:30hrs Monday 9th November 2020

If this package is of interest to your company please contact the Managing QS [Adrian Paddock] by e-mail on [email protected], by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

Additional information: A47 GUYHIRN JUNCTION SCHEME NOTIFICATION OF SUBCONTRACT GROUNDWORKS PACKAGE

The A47 Guyhirn Junction Project is the first of series of 5 projects on the A47 Corridor that Galliford Try are delivering with Highways England through the Regional Delivery Programme - East. The project involves increasing the size of the existing roundabout and approaches to improve capacity. The roundabout is situated at the junction with the A141 some 20km east of Peterborough To enable to successful delivery of the project we are seeking to procure a specialist groundworks subcontractor with experience of delivering major highways projects. The scope of works will involve:- We are seeking to procure a Groundworks Package for the works that will encompass the following elements:

• Main Compound Establishment • Enabling Works • General site clearance • Drainage • Earthworks • Sub Base • Kerbs & Footways (excl bituminous surfacing) • Ducts & Chambers for Street Lighting & Traffic Signal installation • Attendance on Statutory Undertakers (details tbc)

The project is forecast to commence on site in February 2021 Subcontractors bidding for this opportunity will be required to demonstrate their capability and capacity for successfully delivering a project of this size and nature and provide examples of similar projects. Timings Deadline for Notifications of Interest 17:30hrs Tuesday 20th October 2020 Deadline for tender submission 17:30hrs Monday 9th November 2020

If this package is of interest to your company please contact the Managing QS [Adrian Paddock] by e-mail on [email protected], by the above deadline for notifications of interest and a link to the subcontract enquiry documentation can be issued.

Categories (CPV)

Similar open tenders

About galliford try

Their tenders, awards, contracts coming up for renewal, decision makers and committee papers.

View buyer profile

Published by the buyer on Contracts Finder archive (Open Contracting) (Open Government Licence v3.0). Always read the original notice before responding.