Skip to content
Tenfell
Awarded contract
Published 16 Jul 2018

Transformer Oil Removal

SOUTH TEES SITE COMPANY LIMITED

Key facts

Contract value
£23,100
Awarded
08 Jul 2018
Contract starts
15 Jul 2018
Contract ends
30 Sep 2018
Procedure
Single tender action (below threshold)
Buyer type
Other public body

Awarded to

SupplierValue
Utility Oils Limited£23,100

Description

As part of a wider refurbishment project on the South Tees Site Company's (STSC) 66kV High Voltage Distribution network, STSC wish to appoint a suitably qualified and experienced provider to drain, store, recondition, and refill two 66kV to 11kV plant main power transformers (referred to as T67 & T68) and associated equipment.

The service is to include the supply labour and specialist equipment for the following for each transformer (2 off):

Stage 1 (Transformer No. 1) • Removal of transformer oil from a the 30MVA transformer main tank, cooler, tank tool gear and associated pipework, volume of oil approximately 3401 gallons. Deadline: oil to be removed by 13th July 2018 • Off-site storage of oil at a suitable facility for approximately 30 days • Application of Nitrogen or Dry Air blanket to the transformer No.1 to maintain the suitable preservation of the transformer internal parts & components: o Provision, use, and connection of Dry air machine at site o Connect pipework and satisfactorily supply the transformer main tank with Dry Air o Connect Nitrogen bottle, regulator & connections, etc. • Recondition oil* and re-fill** • Oil processing pass within the transformer tank, cooler bank and pipework

Stage 2 (Transformer No. 2) • Removal of transformer oil from a the 30MVA transformer main tank, cooler, tool gear tank and associated pipework, volume of oil approximately 3401 gallons • Off-site storage of oil fat a suitable facility for approximately 30 days • Application of Nitrogen or Dry Air blanket to the transformer No.2 to maintain the suitable preservation of the transformer internal parts & components: o Provision, use, and connection of Dry air machine at site o Connect pipework and satisfactorily supply the transformer main tank with Dry Air o Connect Nitrogen bottle, regulator & connections, etc. • Recondition oil* and re-fill** • Oil processing pass within the transformer tank, cooler bank and pipework

The wider project is due to commence on the 16th July 2018 and the first transformer will be required to be drained prior to this date.

Full details can be found in the ITT document and supporting information attached.

Additional information: All communication relating to this tender must be made via the Procurement Team, email: [email protected]

Please use this email address to: • Confirm intention to submit a tender • Raise any questions during the tender period • Return the completed tender

Categories (CPV)

Similar open tenders

About SOUTH TEES SITE COMPANY LIMITED

Their tenders, awards, contracts coming up for renewal, decision makers and committee papers.

View buyer profile

Published by the buyer on Contracts Finder archive (Open Contracting) (Open Government Licence v3.0). Always read the original notice before responding.